Home > Resources - Recommended Schedule of Instructions for Energising Power Transformer  
 
RECOMMENDED SCHEDULE OF INSTRUCTIONS FOR ENERGISING POWER TRANSFORMER:
Part 1 | Part 2

1. CONSERVATOR :

a) Check the oil level in the conservator. If the level is low than the optimum mark indicated on the oil level gauge, it should be topped with proper grade of transformer oil having suitable breakdown voltage value.

b) The tightness of the cap/plug of the oil filler pipe, drain plug or drain valve should be checked .

c) The oil level gauge of the conservator should always be kept clean so that the oil level is visible from a short distance.

2. BUCHHOLZ RELAY

a) The observation glasses should show that the buchholz relay is properly filled with oil. If necessary, bleeding can be done from the two cocks. The drain plug should be tight and no leaking should be there.

b) The cover on the connection chamber should be opened to observe whether connections are properly tight.

3. SHUT OFF VALVE

This should always be in fully open position while the transformer is being energised.

4. BREATHER

a) The plug at the end of the breather pipe is to be removed and breather fitted on to the pipe along with the fly nut.

b) It is necessary before fitting the breather to observe the colour of the silicagel. If necessary, the breather should be opened and the silicagel properly dried up so that its colour is perfectly bluish.

c) The chamber at the bottom of the breather should be filled in with dry transformer oil up to the level marked.


5. DIAL TYPE THERMOMETER

If it is provided with alarm and trip contacts, these should be set to proper temperature before energising the transformer. For guidance purposes, it may be mentioned here that a transformer having temperature rise of 45/55°C, the trip contact should be set at ambient temperature plus 45°C and the alarm contact will be 5° - 10° prior to this.

6. WINDING TEMPERATURE INDICATOR

This will be set in the same way as the dial type thermometer excepting that the trip contact should be set at ambient temperature plus 55°C.

7. MARSHALLING BOX:

The windows of the marshalling box should always be kept clean so that the readings of the oil temperature indicator and winding temperature indicator can be easily read from outside. Some dehydrating agent may be kept inside the marshalling box so that the box is kept always in dry condition. Do not keep the dorr of marshalling box open. It must be locked.

8. EXPLOSION VENT

a) In case an equaliser pipe connection is provided, the valve in the pipe should be kept in open position before the transformer is energised.

b) If the explosion vent is provided with an air release device, this should be opened once to release any pressure generated inside and then it should be closed.

c) The diaphram of the vent should be intact.

Click Here to Continue to Part 2
© 2004. Trafo Electrics. No part of this above-given recommended schedule can be used in any manner, without prior notifcation & appropriate permission by Trafo Electrics. Anything done will be taken as illegal.
Click Here To Know More About Trafo Electrics!
 
 
 
 
 
About Us | Blog | News & Events | Facts | Classifieds | Directory Services | Message | Feedback | Site Map | Privacy Statement | Contact Us
© 2003. All Rights Reserved with Trafo Electrics Pvt. Ltd. Designed & Maintained By General Data Pvt. Ltd.
For more information, e-mail us at info@electricityindia.com. Site Best Viewed in MS Internet Explorer with 800*600 resolution.
Facebook Twitter LinkedinBlog